Spain has included the third electricity interconnection with Morocco in its 2025-2030 network development plan, with the project’s estimated cost rising to €434.6 million, according to documents published in the Spanish Official Bulletin on November 12.
The strategic environmental declaration, dated November 3, marks a new administrative step but does not constitute final construction approval or a launch of works.
The Spanish National Commission on Markets and Competition (CNMC) noted that the investment figure has increased by about 85% from the €234.7 million listed in the previous 2021-2026 plan.
This rise comes despite scaled-back technical parameters: the planned submarine cable length has been reduced from 52 km to 42 km, and the number of electrical positions cut from six to four.
The CNMC has requested clearer justification for the higher unit costs, details on the cost-sharing arrangement with Morocco, and a more thorough assessment of economic benefits for Spanish consumers.
The 700 MW link would raise the total interconnection capacity between the two countries from 1,400 MW to 2,100 MW.
Originally announced in a 2019 memorandum of understanding and targeted for commissioning before 2026 at a cost of around €150 million, the project is now aligned with a 2030 horizon.
Technical challenges in the Strait of Gibraltar and supply-chain constraints could push completion to 2033 or 2034, the regulator warned.
The new line is expected to strengthen energy security, support renewable energy integration, and expand bidirectional electricity trade. Morocco currently remains a net importer of Spanish power.