Construction works of the first phase of Morocco’s Noor Midelt solar project, the largest in Africa, will be launched on January 15, 2027 after years of delay and a redesign of the original plan.
The project will comprise a 632.8-MWp photovoltaic (PV) plant and a 1,323.96-MWh battery energy storage system (BESS), according to a statement issued by China Energy Engineering International Group.
The construction period is set to run until the middle of July, 2028. The project is located in the Midelt region of central Morocco. Its current configuration differs significantly from the original plan, which envisaged an 800-MW hybrid solar complex combining concentrated solar power (CSP) and PV technology.
The project was initially awarded in 2019, when Morocco’s sustainable energy agency MASEN selected a consortium comprising France’s EDF, Abu Dhabi-based Masdar and Moroccan developer Green of Africa following an international competitive tender.
Construction was originally expected to begin in 2019, with the plant scheduled to enter operation in 2022. However, the project was held up by prolonged negotiations between MASEN and the state-owned utility ONEE over technical and financial terms, particularly changes to the CSP component. The process was further affected by the Covid-19 pandemic and the resulting supply-chain disruptions and cost increases.
A new phase in the project’s development began in August 2026, when a consortium of Energy China International, Southwest Electric Power Design Institute and China Energy Construction Group signed an EPC contract for the first phase of the Midelt solar-storage project. The contract covers survey, design, equipment supply, construction, installation and commissioning.
The Chinese contractor described the scheme as set to become Africa’s largest single-site solar-storage project once completed. The addition of large-scale battery storage is expected to help balance the output of the PV plant and improve the flexibility and reliability of Morocco’s power system.